Twelve Days Of Living In A House Getting New Siding

The dumpster landed in our driveway on a Sunday evening in July, which is how our two kids found out the project was real. By seven the next morning there were ladders against the west wall, both dogs were barking at an air compressor, and I was standing outside with a cup of coffee I never drank. Twelve days, the estimate said. We had spent six weeks comparing quotes for hardie board siding draper ut and almost no time at all on what living inside the house during the work would feel like.

So here is the thing I wish someone had told us early. The material you pick matters far less than whether the schedule is written down before the first cut and updated the same day it slips. A crew that sequences an occupied re-side up front, tells you which wall comes off when, and texts you the moment weather moves a step is worth more to a household of five than any upgrade line on the estimate.

Pick The Month Before You Pick The Crew

We signed in April and asked for July, and our contractor pushed back before he agreed. Dry days are what an exterior job runs on, and along the Wasatch Front you get a long run of them in midsummer, which matters more than it sounds when a whole wall is open to the weather. The tradeoff is heat. Crews start at 6:30 to stay ahead of it, so if anyone in your house sleeps past seven, that habit ends for two weeks. I checked the National Weather Service hourly forecast page every morning for the two weeks before our start date, which costs nothing and turned out to be the most useful thing on my phone. A Family Handyman piece from June 2026 that my husband kept sending me puts exterior paint on a three to five year failure cycle, with hardboard needing recoating more often than vinyl or composite, and that was the argument that finally moved us off repainting what we already had. In practice, choosing a month usually means choosing which inconvenience you would rather live with.

READ ALSO  Clear View Glass Company: Your Trusted Local Experts in Glass and Window Services

See also: How to Fit a Barrel Sauna into a Small Backyard

Cutting Dust Is The Part To Plan Around

Cutting fiber cement releases respirable crystalline silica, and that is the piece of this job to plan your household around. Keep children, pets and anybody not on the crew out of the cutting area while a saw is running, keep the windows on that side of the house closed, and expect the crew to be using dust-collecting saws or wet cutting methods with respiratory protection on. Ours set the cut station at the back fence line, and moved it twice when the wind swung around. When I read reviews for hardie board siding draper ut before we signed, dust control was the one subject almost nobody brought up, and it ended up shaping our entire daily routine.

How much of that dust actually got inside a closed house over three cutting days, I cannot tell you. Nobody measured it, I have not found a number I trust for an occupied home mid-project, and I am wary of anyone who quotes one confidently. So we did the practical things instead: the air conditioning ran on recirculate, we swapped the filter halfway through, the dogs got a long morning walk rather than yard time, and the toddler napped on the east side while the west wall was coming apart.

Day By Day Through A Twelve Day Job

Day one is demolition, and it is the loudest day of the whole job. Old siding comes off in sheets, the dumpster fills, and by dinner you are looking at bare sheathing plus every repair anyone ever made to that wall. Day 2 and day 3 were rot repair and house wrap, quiet work that felt like progress after the noise. By the end of the first week the wrap, flashing and trim were on and the first courses of board were up.

READ ALSO  How Does Regular Drain Cleaning Prevent Plumbing Disruptions?

Day 4 through the middle of the second week is when the saw runs most, and that stretch is worth arranging your calendar around. A NIOSH hazard alert issued with OSHA reports that some engineered stone products run as high as 95% crystalline silica by weight, and it calls for wet cutting or dust collection plus respiratory protection whenever silica-bearing material is cut or ground. Fiber cement sits well below that share, but the control is the same one, which is why a good crew treats the cut station as a fixed part of the site plan instead of wherever the sawhorses happened to land. I stopped apologizing for asking about it after the first morning.

Day 9 was caulking and touch-up and the punch list, which is where a crew either earns the rest of the money or does not. Ours walked the house with me twice, once in flat morning light and once at dusk, because different flaws show at different hours. Day 12 was cleanup, a magnet sweep for nails across the lot, and a final walk-through with the warranty paperwork.

Twelve days with five people, two dogs and a house open to the weather is survivable, and the gap between survivable and miserable is information. We knew which wall was next, we knew which mornings would be loud, and we knew the day the schedule slipped because somebody told us rather than because we noticed. Ask for the sequence in writing before you sign. Ask where the cut station goes and who calls you when the plan changes. Those questions cost nothing, and they are what turned a torn-open house into an ordinary two weeks.